f1119ffcf5 Support working copies and separate allocate + activate steps for resources/leases in Drydock
Summary:
Ref T9253. For resources and leases that need to do something which takes a lot of time or requires waiting, allow them to allocate/acquire first and then activate later.

When we allocate a resource or acquire a lease, the blueprint can either activate it immediately (if all the work can happen quickly/inline) or activate it later. If the blueprint activates it later, we queue a worker to handle activating it.

Rebuild the "working copy" blueprint to work with this model: it allocates/acquires and activates in a separate step, once it is able to acquire a host.

Test Plan: With some power of imagination, brought up a bunch of working copies with `bin/drydock lease --type working-copy ...`

Reviewers: hach-que, chad

Reviewed By: hach-que, chad

Maniphest Tasks: T9253

Differential Revision: https://secure.phabricator.com/D14127
2015-09-21 04:46:24 -07:00